MARCH 2023

Construction progress of Thu Thiem Zeit River updated to March 2023:

  • Tower 1 & Tower 2: Civil work is in progress for the 20th floor.

Finishing work:

  • Tower 1: Undergoing bricklaying on the 15th floor, and MEP installation up to the 11th floor;
  • Tower 2: Undergoing bricklaying on the 16th floor, and MEP installation up to the 13th floor;
  • Podium: Undergoing bricklaying, plastering for community and amenity spaces.