JANUARY 2023

Construction progress of Thu Thiem Zeit River updated to January 2023:

  • Tower 1: Civil work is in progress for the 15th floor;
  • Tower 2: Civil work is in progress for the 14th floor;
  • Podium: Flooring is in progress for the 5th floor.

Finishing work:

  • Tower 1: Undergoing bricklaying, plastering, tiling, and MEP installation;
  • Tower 2: Undergoing bricklaying, plastering.