Construction progress of Thu Thiem Zeit River updated to August 2023:
- Two towers T1 and T2 had finished topping up;
- Tower 1: Tiling from the 7th to the 17th floor; exterior painting from the 6th to the 23rd floor; plastering from the 6th to the 18th floor; interior painting phase 1 is underway from the 6th to the 12th floor. Meanwhile, the ceiling, door system, and tiling inside apartments are on schedule, having finished up to the 13th floor;
- Tower 2: Bricklaying up to the 29th floor; interior plastering up to the 24th floor and exterior plastering up to the 28th floor; painting and tiling work is being carried out to the 15th floor; and installing hardwood flooring up to the 18th floor;
- Amenities and low-rise areas are also being built synchronously;
- The parking basements’ construction is in finishing steps.