APRIL 2O23

Construction progress of Thu Thiem Zeit River updated to April 2023:

  • Tower 1 & Tower 2: Civil work is in progress for the 23rd floor.

Finishing work:

  • Tower 1 & Tower 2: Undergoing bricklaying on the 18th floor, and MEP installation (mechanical, electrical and plumbing) up to the 14th floor;
  • Podium: Undergoing bricklaying, plastering on the 4th floor.