MARCH 2024
As of March 2024, Thu Thiem Zeit River has entered the completion phase preparing for handover to future owners.
- The exterior has completed 70% of progress in painting, and finishing steps;
- The interior has finished 100% with wall cladding, ceiling, main doors installation, balconies, electrical systems, water heating systems, furnishing bathrooms and kitchens…;
- Tower T1 will continue to be furnishing basic elements such as cupboard, stove, air conditioner, wardrobe, pantry … to ensure the progress of handing over to the customer follows as planned.
- Simultaneously to the Tower T1, Tower T2 has been completing the exterior with painting and coating the entire tower, including the walls and ceilings of balconies;
- The interior has also completed installing lighting system, smart wall pad, air conditioner, water heating systems, floor tiling, glass doors…;
- Tower T1 will continue to be furnishing elements in the living rooms, kitchens, bedrooms (shelves, wardrobes) and wall cladding.